CASE STUDY
Recovering a Chemical Manufacturer’s Productivity with Batch Cycle Time Reduction
The completed project made the process safer and recovered 30% of the lost cycle time, giving an ROI of well under one year.
OBJECTIVE: The chemical manufacturer needed to recover productivity losses caused by an unexpected increase in cycle time after a migration of the plant’s legacy Emerson PROVOX™ to a DeltaV™ distributed control system (DCS).
The third-party migration from legacy Emerson PROVOX™ to DeltaV™ DCS increased the cycle time on a train of eight chemical reactors by approximately 6%, costing the end user more than one million dollars per month in lost productivity. The objective was to investigate where time was being lost in the batch process due to logic changes during migration and recover as much time as possible to increase productivity.
CHALLENGE: A safety issue required a project pivot and scope change during the project. A potentially dangerous safety hazard associated with the original migration was identified and the system was operating in an unknown state.
The DeltaV™ logic was skipping over the task of confirming valve positions before moving to the next step in the batch. This issue needed to be addressed before moving forward with the cycle time reclamation aspect of the project. Addressing the lack of valve position confirmation, the additional logic forcing the DeltaV™ to wait for the valve positions to confirm caused even slower cycle times than the project started with, so the gains shown in the initial proof of concept became unattainable.
SOLUTION: Move the existing logic from being executed in phases to being executed in equipment modules.
A solution was formulated to move the existing logic from being executed in phases to being executed in equipment modules. Under this scheme, each phase became one equipment module. This alleviated many of the pressure points the unit faced.
A full retest of logic was not required since the existing, fully-tested logic was only relocated and not changed.
The equipment modules were assigned to new controllers since they had no I/O associated with them. This took some strain off the existing controllers and allowed the batch logic to execute on lightly-loaded controllers.
While the execution time of phases is tied to the execution time of the unit module in DeltaV™ and requires them all to execute with the same scan rate, the individual equipment modules can have unique scan times. This allowed for some sections of code which were mostly calculations or flags to execute much faster than sections of code that communicated with the control devices in the field.
A proof-of-concept project was executed and lab testing showed that about 85% of the time associated with loading phases and executing initialization logic (setting flags) in DeltaV™ could be eliminated using this new philosophy.
Results: Safer and More Consistent
Additional logic was implemented to wait for the confirmation of valve positions, making the operation safer and more consistent. The implemented cycle time improvements were logic driven and did not require a retest of the logic, saving cost and downtime. The logic was moved from being executed in phases to being executed in modules, allowing different scan rates for different equipment and eliminating the associated dead time. The equipment modules without I/O were assigned to new controllers, allowing the batch logic to execute more quickly on lightly-loaded controllers.
The completed project made the process safer and recovered 30% of the lost cycle time, giving an ROI of well under one year.
Stay Informed
Read from our blog featuring Hargrove Teammates
Six Questions to Properly Scope Your SCADA and IIoT System
Investing in a supervisory control and data acquisition (SCADA) system is not just an investment in process control. It is an [...]
Batch Management Solutions
Imagine a production line at your chemical manufacturing plant produces yellow paint that is used for traffic marking. As client demand [...]
Reduce Risk with a DCS Migration
Working at a manufacturing facility may often require scouring the web to purchase critical replacements or hardware for operating systems that [...]
Other Areas of Service
Subscribe to Our Newsletter
Stay up to date on the latest Hargrove News & Insights.
CONTACT US
Let’s Make your Facility Safer.
With Hargrove, you get the right experience from the right people in system integration working alongside you to meet and exceed your expectations. Working together as one team – that’s Hargrove.